The City of Brandon is working in coordination with the Province of Manitoba and their partners to provide updates regarding 18th Street Reconstruction Project.
18th Street Reconstruction Alert
Starting tomorrow, September 18th, Zenith Paving Ltd. will begin milling and placing new asphalt on 18th Street from Aberdeen Ave to Rosser Ave.
The project will be completed in stages. Expect minor concrete repairs, asphalt milling, and paving.
- Stage 1 – Rosser Ave to Louise Ave Southbound
- Stage 2 – Louise Ave to McTavish Ave Southbound
- Stage 3 – McTavish Ave to Park Ave Southbound
- Stage 4 – Park Ave to McTavish Ave Northbound
- Stage 5 – McTavish Ave to Louise Ave Northbound
- Stage 6 – Louise Ave to Rosser Ave Northbound
- Stage 7 – Park Ave to Queens Ave Southbound
- Stage 8 – Queens Ave to Park Ave Northbound
- Stage 9 – Queens Ave to Aberdeen Ave Southbound
- Stage 10 – Aberdeen Ave to Queens Ave Northbound
Key Notes:
- Work will progress from Rosser Ave to Queens Ave, both southbound and northbound in sections.
- Please drive safely and avoid the area if possible. It is especially important to keep children and pets away from construction areas.
- Business access will be maintained, but driveway access may be restricted at times. Please reach out to specific businesses for more information.