Province Releases Update on Daly Overpass Project


Due to growth in the region and the importance of PTH 10 as a major route, the current three-lane Daly Overpass structure has created a ‘bottleneck’ in the system. To remedy the situation, Manitoba Infrastructure is constructing a new four-lane facility to replace the 50+-year-old overpass. The construction period is expected to run until Late 2023. MI will continue to provide project updates throughout the construction period.

 

Photo credit (www.gov.mb.ca)

 

The project includes the following components:

– A new four-lane bridge over the CP Rail facility

– A separate new pedestrian/active transportation bridge just east of the new bridge

– New on/off ramps to connect 18th street with Pacific Avenue

– Property acquisitions to enable construction, improve sight lines and improve the functionality of the bridge

Photo credit (www.gov.mb.ca)

 

The project team has met with many groups and individuals who are likely to have an interest in this project. Some of these groups include:

– City of Brandon departments

– CP Rail

– Utilities

– Adjacent landowners and businesses

– Nearby residents

– Emergency services

– Transit and active transportation interests

– Organizations and interest groups

– Bridge users

– Others, as they were identified throughout the project

MI will continue to communicate with the general public throughout the construction period.

 

Photo credit (www.gov.mb.ca)

 

The estimated timeframes for key project milestones are as follows: Site preparation work (including soft dig operations for utilities) to take place in November 2020 (Completed) Demolition contract to be advertised on December 17, 2020, Building demolitions (including the Kullberg building) will begin in January 2021 (Completed) and are expected to be substantially complete by April 2021.

Offline bridge construction is anticipated to begin in May 2021, First traffic changes will likely occur in May 2021, Construction completion including demolition of the existing bridge is targeted for late 2023.

Questions and comments about the project can be directed to: dalyoverpass@gov.mb.ca

For more information visit the Manitoba Government's website here.

Province of Manitoba News Release